Thursday 9 May 2019:

General news 

  • Portable changerooms in 50 metre pool outdoor area will arrive on Monday 13 May and will be ready to use by Thursday 16 May.
  • The Pearcedale Parade car park will be closed on Monday 13 May from 5am – 3pm to allow the crane to place the portable changeroom.
  • The first stage of roof works affecting the Gymnasium level (Functional Training Area and toilets) will start on Wednesday 15 May. We anticipate the Functional Training Area and toilets will be unavailable for up to three weeks, however it may be less.
  • All the equipment from the Functional Training Room will be relocated to other areas of the Gymnasium and Studios with exception of the main rig/rack.
  • Major demolition works of 25m pool mezzanine and change rooms have been completed.
  • Overhead air handling ducts in main 25 metre pool area have been removed.
  • New heaters for 25m pool and leisure pool have arrived and been placed into position. 

Thanks again for your patience and understanding throughout these works.



Friday 12 April 2019:


General news:

  • Planning to use the pool? Check what lanes are available before you visit 
  • From 15 April our builders will start the removal of the mezzanine balcony. During the week this will cause louder-than-usual construction noises throughout the centre.
  • From 15 April the 50-metre pool will change to a 2x25-metre format
  • Temporary raised flooring will be installed in a portion of the 25-metre pool from Monday 15 - Thursday 18 April.
  • Dry changerooms will be installed in the foyer on Tuesday 23 April.

Friday 5 April 2019:

General news:

  • Xerri Group has been appointed as builder and will commence onsite from Monday 8 April.
  • 25m pool, leisure pool, spa, sauna and adjacent changerooms will be unavailable from Monday 8 April.
  • The gym area will remain open and will not be impacted at this moment.
  • There will be noise due to demolition of 25m pool mezzanine from Wednesday 10 April – Thursday 18 April.
  • From Monday 15 April, the 50m pool will change to a short-course 2x25-metre format.
  • Portable changerooms to be located near 50m pool are being arranged for the start of term 2 swimming lessons.
  • Our Customer Experience Officers will be available to talk you through any questions you may have. You can call them on 9205 2670 or visit in centre.

Parking: 

  • Improvements to the Pearcedale Parade car park will occur over the school holidays to increase the number of available car parks in this area.
  • Part of the carpark off Tanderrum Way will be unavailable throughout the duration of the works (refer to map)
    Please refer to this map for more information on parking

BALC parking.JPG

 

 