  Friday 23 August 2019

  • Following the collapse of the Head Contractor for the works at Broadmeadows Aquatic and Leisure Centre, Hume City Council has become the project’s owner/builder and will complete all works that were originally planned, with the exception of the windows which will be replaced at a later date.
  • Council is pleased that many of the original sub-contractors working on the project were able to be reengaged by Council.
  • This took time to negotiate, and along with inclement weather, there has been some delays in progress.
  • From early October, users of the centre will likely get a taste of the newly redeveloped sections.
  • The roof replacement has almost been completed over the 25-metre pool area and is progressing over the 1st floor fitness area. Weather permitting, the gym area is expected to reopen upstairs in early October.
  • The structural work and fit out of services in the changerooms has been completed. Tiling, painting and fittings will be complete in the coming weeks. The changerooms are expected to reopen in early November.
  • Upgrades to equipment in the 25-metre pool plant room is progressing, a new ceiling is being installed and the painting of the pool hall is almost complete. Weather permitting, the 25-metre pool is expected to reopen in early December. Council acknowledges this will affect a portion of Learn to Swim participants, and leisure centre staff will be in contact those affected to discuss their options.
  • While the delay in works is unfortunate, Council has been working tirelessly to ensure works continued given the circumstances. We acknowledge many people are eagerly anticipating the full reopening of the centre, and we are just as excited to see it complete.
  • The next Q&A: Meet the Management session will be on Wednesday 4 September from 10.30am - 11.30am in the centre foyer. 

 


Thursday 4 July 2019

  • Electrical works have been completed.
  • Redevelopment works are recommencing following efforts from Council to retain some of the sub-contractors already working on the project.
  • This means that, from Thursday 11 July for approximately six weeks, a Pop-Up Gym will be available in the Centre as roof works continue. During this time the gym floor will be unavailable.
  • Group fitness classes will run on a modified timetable during the same period. This timetable will be available from Friday 5 June.
  • For more information or to discuss your membership options, please call, email or visit us in centre.

Wednesday 26 June 2019

  • Our Centre will be closed on Wednesday 3 July and Thursday 4 July for electrical upgrades.
  • Members can access Splash Aqua Park and Leisure Centre and Sunbury Aquatic and Leisure Centre on Wednesday 3 July and Thursday 4 July.
  • A revised Group Fitness timetable will operate from the Netball Stadium.
    • Wednesday 3 July 9.20am BODYSTEP
    • Thursday 4 July 9.20am CIRCUIT
    • Thursday 4 July 6pm BODYSTEP
  • School holiday program and court bookings will continue as normal in the Netball Stadium on Wednesday 3 July and Thursday 4 July.
  • Further details regarding roof replacement in the first floor fitness area will be announced soon.
  • Please note inclement weather may delay the works and we will advise accordingly.

 


Wednesday 12 June 2019:

Hume City Council is disappointed to learn that the head contractor for the upgrades and works at Broadmeadows Aquatic and Leisure Centre has gone into liquidation. During this time the centre will continue to operate in its current state until further notice.
The head contractor, Xerri Group Pty Ltd, was responsible for completing project. Works will temporarily stop on-site while Council investigates the necessary steps to finish the project.

  • We will be open on Saturday 15 and Sunday 16 June. The scheduled centre-wide shut down for electrical upgrades is postponed. A new date will be announced later.
  • The upstairs gym area will remain open until further notice (the temporary pop-up gym will likely happen later)
  • Group Fitness classes will continue as normal until further notice. For the latest group fitness timetable please check here.
  • Swim School classes scheduled to run on Saturday 15 and Sunday 16 will now continue. Leisure Centre staff will try and contact the families individually.

 


Friday 7 June 2019:

  • Centre closure on Sunday 9 June has been postponed.
  • Our Centre will now be closed on Saturday 15 June and Sunday 16 June due to electrical upgrades. Swim school families who have a lesson on these dates will not be charged. Members can access Splash Aqua Park and Leisure Centre and Sunbury Aquatic and Leisure Centre on Saturday 15 June and Sunday 16 June.
  • From Monday 17 June for approximately six weeks, a Pop-Up-Gym will be available in the centre from as roof works continue. During this time, the gym floor will be unavailable. 
  • Group fitness classes will run on a modified timetable during the same period which will be released fortnightly.  Click here for the latest timetable.
  • For more information on the Pop-Up-Gym and your membership options during this time, click here.
  • If you have more questions, we invite you to an evening Meet the Management Q&A where you can ask questions about the works on Wednesday 13 June from 6pm – 7pm

Monday 27 May 2019: 

  • Our Centre will be closed Sunday 9 June due to electrical upgrades. Swim school families who have a lesson on this date will not be charged. 
  • Members can access Splash Aqua Park and Leisure Centre and Sunbury Aquatic and Leisure Centre on Sunday 9 June.
  • Public holiday hours will also be in effect on Monday 10 June (8am – 12pm)
  • From Tuesday 11 June - Monday 29 July, a Pop-Up-Gym will be available in the centre from as roof works continue. During this time, the gym floor will be unavailable. 
  • Group fitness classes will run on a modified timetable during the same period. This timetable will be available from Tuesday 4 June. Click here for the latest timetable.
  • If you have more questions, we invite you to our Meet the Management Q&A where you can ask questions about the works on Friday 31 May from 9.30am - 10.30am

Thursday 9 May 2019:

  • Portable changerooms in 50 metre pool outdoor area will arrive on Monday 13 May and will be ready to use by Thursday 16 May.
  • The Pearcedale Parade car park will be closed on Monday 13 May from 5am – 3pm to allow the crane to place the portable changeroom.
  • The first stage of roof works affecting the Gymnasium level (Functional Training Area and toilets) will start on Wednesday 15 May. We anticipate the Functional Training Area and toilets will be unavailable for up to three weeks, however it may be less.
  • All the equipment from the Functional Training Room will be relocated to other areas of the Gymnasium and Studios with exception of the main rig/rack.
  • Major demolition works of 25m pool mezzanine and change rooms have been completed.
  • Overhead air handling ducts in main 25 metre pool area have been removed.
  • New heaters for 25m pool and leisure pool have arrived and been placed into position. 

Thanks again for your patience and understanding throughout these works.


Friday 12 April 2019:

  • Planning to use the pool? Check what lanes are available before you visit 
  • From 15 April our builders will start the removal of the mezzanine balcony. During the week this will cause louder-than-usual construction noises throughout the centre.
  • From 15 April the 50-metre pool will change to a 2x25-metre format
  • Temporary raised flooring will be installed in a portion of the 25-metre pool from Monday 15 - Thursday 18 April.
  • Dry changerooms will be installed in the foyer on Tuesday 23 April.

Friday 5 April 2019:

General news:

  • Xerri Group has been appointed as builder and will commence onsite from Monday 8 April.
  • 25m pool, leisure pool, spa, sauna and adjacent changerooms will be unavailable from Monday 8 April.
  • The gym area will remain open and will not be impacted at this moment.
  • There will be noise due to demolition of 25m pool mezzanine from Wednesday 10 April – Thursday 18 April.
  • From Monday 15 April, the 50m pool will change to a short-course 2x25-metre format.
  • Portable changerooms to be located near 50m pool are being arranged for the start of term 2 swimming lessons.
  • Our Customer Experience Officers will be available to talk you through any questions you may have. You can call them on 9205 2670 or visit in centre.

Parking: 

  • Improvements to the Pearcedale Parade car park will occur over the school holidays to increase the number of available car parks in this area.
  • Part of the carpark off Tanderrum Way will be unavailable throughout the duration of the works (refer to map)
    Please refer to this map for more information on parking

BALC parking.JPG

 

 


Updated : 4:24 PM, 23 August 2019