Greenvale Recreation Reserve Upgrades

  • Project statusDesign
greenvale recreation reserve cricket ground

We’re upgrading and expanding Greenvale Recreation Reserve to support the needs of our growing community.

What we're doing

Hume City Council is upgrading and expanding facilities at the Greenvale Recreation Reserve to support the community to get outdoors and involved in sport locally. These works will provide more spaces for the local community to get active and engage in local sport as well as provide facilities to support high level sport. 

These projects include:

  • indoor cricket hub
  • sports oval four
  • car park, landscaping and services upgrade
  • new carpark and access road to the Greenvale Equestrian Centre

Why we're doing it

Greenvale Recreation Reserve is the largest and most diverse sporting and recreation open space area servicing the Greenvale Community.

The sporting facilities currently include:

  • three sports ovals
  • five cricket practice nets
  • a turf practice wicket area
  • nine tennis courts
  • three equestrian sand arenas
  • an equestrian course

With significant residential development in Hume City, the population of Greenvale is projected to exceed 26,000 people - our facilities need to be expanded and upgraded to meet increasing demands and needs.

Project details and timelines

Indoor cricket hub

Project status: Construction 
Project value: $10.8 million
Due to be completed: June 2024

The indoor cricket hub will include a 6-lane synthetic turf cricket nets, changing spaces and meeting rooms. 

The hub will also include a Pavilion to serve the proposed Sports Oval four, which will include home and away change rooms, umpire rooms, medical rooms and a canteen.

greenvale indoor cricket hub
Architect concept image of Indoor Cricket Hub 

Partnerships
This project is being supported by the Victorian Government through the 2019 -2023 Community Cricket Program fund. 

Sports oval four

Project status: Design
Completion of design: April 2023
Construction estimated to commence: September 2023

This project involves the development of a new AFL / Cricket Oval including a turf wicket table with 7 lanes, sports oval lighting for football night matches, oval irrigation, drainage, player benches, fencing and an electronic scoreboard.

ac4c20f3-2159-46c0-a63f-45403b34240d.jpeg
Architect concept image of oval and Indoor Cricket Hub 

Carpark, landscaping and services upgrades

Project Status: Design
Design completed: April 2023
Construction estimated to commence: September 2023 

We're building a new car park with approximately 60 car spaces, a bus drop-off / pick-up zone and lighting to service the new indoor cricket facility and proposed fourth sports oval. There will also be upgrades to the existing water and power services to meet the requirements for the new facilities.

New carpark and access road to the Greenvale equestrian centre

Project Status: Construction since March 2023
Due to be completed: May 2023
Project Value: $300,000

We're constructing a new car park and gravel access road to the Greenvale Equestrian Centre. This will include approximately 43 spaces to service the new equestrian pavilion, and a gravel access road to provide all weather access to the user groups facilities across the reserve.

Location

195 Section Road, Greenvale 3059  View Map