This page is to assist developers and their agents with the Engineering and Landscape requirements for large scale developments and to clarify the process for submitting detailed design forms to Council.
Please read our upcoming changes to Subdivisions Engineering and Landscape Processes - Industry Communication(PDF, 289KB).
If you are seeking information about subdividing an existing residential property, please see Subdividing residential property
Before submitting your Functional Layout Plan (FLP) form to Council, you will need to have all required documents ready to be uploaded. Refer to the FLP Submission Guidelines(PDF, 102KB) for assistance.
Once all required documents are prepared, complete the Functional Layout Plan submission form, and attach the Functional Layout Plans.
Functional Layout Plan (FLP) Form
Alternatively download the Functional Layout Plan printable form(PDF, 281KB).
The Engineer assigned to your project will review the FLPs and contact you with any Request for Further Information comments.
Once all RFI comments have been addressed, approved plans will be sent to your nominated email address.
Before submitting your civil detailed design form to Council, you will need to have all required documents ready to be uploaded. This includes your design drawings, traffic assessment report and many other important documents.
See required documents list below
Once you have the required documents ready, you are ready to submit your design submission to Council. This can be done online or by using our printable form. Applicants must use either of these forms when submitting their design to Council.
Civil Detailed Design Form
Alternatively download the Civil Detailed Design Printable form(PDF, 342KB).
Approval of Detailed Design Plans can take 30 working days from submission to finalise. This timeline allows for 8 days administration time. If Council requires further information from you when making a decision, the statutory clock will stop. Please note the stop and start of the clock will be communicated to the applicant. Please see the process tab above for more information about how we handle these submissions.
Once your submission has been fully assessed by an officer, you will be advised of an application outcome. Approval of Detailed Design Plans can take 30 days to finalise excluding additional administration process times.
If your submission is approved, approved plans will be forwarded to your nominated email address.
Before submitting your detailed landscape designs form to Council, you should have the following documents ready to be uploaded:
Once detailed engineering plans have been approved and all required landscape documents are prepared, you can submit your application online or using our printable form.
Landscape Detailed Design Form
Alternatively download the Landscape detailed design printable form(PDF, 368KB).
The review of Detailed Design Plans begins once the submission is received and assigned to a Landscape Officer to review.
If additional information is required, you will be notified by the Landscape Officer directly.
Once all landscape comments have been addressed, approved plans and approval letter will be sent to your nominated email address.