Jack Ginifer Reserve Subsurface Drainage Project
- Project statusConstruction
What we're doing
We're upgrading the sportsground to provide a safer, more reliable playing surface for the community. Works will improve drainage, irrigation and turf quality to support year-round use. The works will include:
Why we're doing it
These works are required as Jack Ginifer Reserve previously had no subsurface drainage and has historically become waterlogged following rain events, limiting use and site access. In addition, the existing irrigation system is outdated and no longer provides efficient or reliable coverage, impacting turf health and overall field performance.
What to expect
Construction works are currently underway. The project is due to be completed prior in late August (weather permitting), prior to the 2026/27 cricket season commencing.
Temporary fencing is in place installed around the perimeter of the work area and the reserve is closed throughout the construction period.
Timing
We appreciate your patience as we work on these improvements at Jack Ginifer Reserve.
These works have required additional time due to several site challenges. The existing soil beneath the turf was unsuitable and had to be replaced with new material that meets performance standards. The irrigation system also needed to be fully redesigned and installed, as the original layout did not provide adequate coverage.
Wet weather further delayed access and construction activities. In addition, changes to surface levels meant extra works were needed to adjust the pavilion and ensure it connects properly with the surrounding area.
Thank you for your understanding as we work to deliver a high-quality and long-lasting outcome for all users.
Location
Carrick Drive, Gladstone Park 3043 View Map
-37.6926074,144.8952005
Carrick Drive ,
Gladstone Park 3043
Carrick Drive ,
Gladstone Park 3043
Jack Ginifer Reserve Subsurface Drainage Project